The original times for lane blockages (6pm to 6am) for the MOW resurfacing project between Beaver Creek Dr and Tates Creek Rd has changed due to nighttime temperatures being too cold for paving.
Starting today 4/28 (and currently in progress), work is scheduled from 9am to 9pm from 4/28 thru 5/1, and 5/4 thru 5/6. At this time, weekend work is not planned.
The inner loop left lane is currently closed from a point just prior to Beaver Creek Dr up to Tates Creek Rd.
The paving plan is to pave one lane at a time from end to end (back and forth) as weather permits.
A recommendation has been made to make every effort to avoid blocking lanes between Alumni and Beaver Creek anywhere close to peak travel times due to heavier congestion in that area.